Environmental Sanitation Engineering ›› 2025, Vol. 33 ›› Issue (2): 71-76.doi: 10.19841/j.cnki.hjwsgc.2025.02.010

Previous Articles     Next Articles

Process Design of Leachate Treatment Project of Dalian Incineration Power Plant under Different Production Standards

SHI Huan, LI Qiang,LIU Yifu, XIAO Yangyi, CHEN Yuting, YUE Lei, LI Mengya   

  1. CUCDE Environmental Technology Co. Ltd.
  • Online:2025-04-28 Published:2025-04-28

Abstract: The sewage treatment station project of the second phase of domestic waste incineration power generation project in the central urban area of Dalian city was designed to partially reuse the effluent and partially discharge it. Among them, the water quality of the recycled part met supplementary water quality requirements of the open circulating cooling water system in the GB/T 19923—2005 Reuse of Urban Recycling Water-Water Quality Standard for Industrial Uses, and the discharge part should comply with the first level A standard of GB 18918—2002 Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant. The main process of leachate treatment is “pretreatment + anaerobic + external MBR+ nanofiltration + reverse osmosis”, and the concentrated solution treatment adopts the process of “material film reduction+reinjection”. The overall operation of the project is good, and the effluent quality is stable and up-to-standard.

Key words: waste leachate, membrane bioreactor, reduction treatment, first level A standard

No related articles found!
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed   
[1] . Status Evaluation of Groundwater Quality of A Waste Landfill Site in Tongliao   [J]. Environmental Sanitation Engineering, 2018, 26(3): 36 -38 .
[2] . Analysis on Characteristics of Stench and Effect of Different Deodorization Processes in Domestic Refuse Transfer#br# Station   [J]. Environmental Sanitation Engineering, 2018, 26(3): 56 -58 .
[3] . Stress Analysis of Steam-water Pipes and Optimized Design of Support-hangers in Waste Incineration Power Plant   [J]. Environmental Sanitation Engineering, 2018, 26(3): 59 -62 .
[4] . Research on Treatment of Water-wall High Temperature Corrosion of Waste Heat Boiler in Municipal Solid Waste#br# Incinerator   [J]. Environmental Sanitation Engineering, 2018, 26(3): 68 -70 .
[5] . Prediction on Generation Quantity of Food Waste in Planning of Kitchen Waste Disposal Facilities   [J]. Environmental Sanitation Engineering, 2018, 26(3): 87 -90 .
[6] . [J]. Environmental Sanitation Engineering, 2018, 26(1): 5 -8 .
[7] . [J]. Environmental Sanitation Engineering, 2018, 26(1): 63 -65 .
[8] . [J]. Environmental Sanitation Engineering, 2018, 26(1): 66 -69 .
[9] . [J]. Environmental Sanitation Engineering, 2018, 26(1): 77 -79 .
[10] . [J]. Environmental Sanitation Engineering, 2018, 26(1): 80 -83 .
Copyright © Environmental Sanitation Engineering
Address: 107#, Weidi Road, Tianjin, P.R.C.    Postcode: 300201
Telephone: 022-28365069   Fax: 022-28365080 E-mail: csglwyjs10@tj.gov.cn
Supported by:Beijing Magtech